PERT/CPM Chart
The table shows some phases of software development. Using available tools or a sheet of paper, prepare a PERT

PERT/CPM Chart The table shows some phases of software development. Using available tools or a sheet of paper, prepare a PERT/CPM chart listing each of the tasks and connect the tasks based on the dependencies. Identify the critical path by shading or marking the tasks in the critical path.


We have an Answer from Expert

View Expert Answer

Expert Answer


1 =========================================== Solution is given below:- TASK PREDECESSOR DURATION (IN DAYS) LATEST START EARLIEST START FLOAT (slack A