(Solved): Given the following network diagram for a project (activity times are in days): a) Determine Earlie ...
Given the following network diagram for a project (activity times are in days): a) Determine Earliest Start time (ES), Earfiest Finish time (EF), Latest Start time (LS), Latest Finish time (LF), and Slack Time for each activity. b) Identify the Critical Path(s). c) What is the expected project duration? d) If the project duration must be reduced by 3 days, which activities will most itkely be atfected?