(Solved): Draw and show the network diagram using the CPM Method and show for each activity on the network di ...
Draw and show the network diagram using the CPM Method and show for each activity on the network diagram the ES, EF, LS, LF, and Total Slack value for each activity. Please show the network diagram with all the ES, EF, LS, LF and Slack values on each activity. -Path (1) =Start ACFH =0+5+7+4+8=24 WEEKS -Path (2)= Start BEFH =0+8+2+4+8=22 WEEKS - Path (3)= Start BDGH =0+8+11+1+8=28 WEEKS - Therefore the critical path is the longest path =(BDGH=28 WEEKS).