construct the network diagram
find the ES EF LS snd LF of each activity
indentify all paths and which path is critical
how long will it take to complete the project
We have an Answer from Expert
View Expert Answer
Expert Answer
From the given datas, the network diagram can be drawn as below... ABCDFEG There are 3 paths in this project, they are 1. A - D - F = 4+6+4 = 14 2. A