Consider the AON graph of a project shown below. Figure 19.19
The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8, respectively. What is the critical path? multiple choice
a. A1, A2, A3, A4, A8
b. A1, A2, A3, A6, A7, A8
c. A1, A2, A5, A7, A8
d. None of these options are the critical path