Home / Expert Answers / Operations Management / consider-the-aon-graph-of-a-project-shown-below-figure-19-19-the-activity-times-are-3-4-2-5-7-pa197

(Solved): Consider the AON graph of a project shown below. Figure 19.19 The activity times are 3, 4, 2, 5, 7, ...



Consider the AON graph of a project shown below. Figure 19.19

The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8, respectively. What is the critical path? multiple choice

a. A1, A2, A3, A4, A8

b. A1, A2, A3, A6, A7, A8

c. A1, A2, A5, A7, A8

d. None of these options are the critical path



We have an Answer from Expert

View Expert Answer

Expert Answer


ANSWER:- Option (c) is correct.
We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe