Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.)
Using the Critical Ratio (CR) schedu
The following jobs are waiting to be processed at Jeremy LaMontagnes machine center. Today is day 250.
Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 250.


We have an Answer from Expert

View Expert Answer

Expert Answer


Critical ratio is calculated by dividing the remaining time by the processing time. Remaining time = Due date - Today's date Processing time = Duratio