(Solved): A master production schedule quantity of 300 units will arrive in week 6. Weekly demand over weeks ...



A master production schedule quantity of 300 units will arrive in week 6. Weekly demand over weeks 3 through 10 is forecasted at 50 units. At present, orders have been booked in various quantities in weeks 1, 2, 3 and 4. What is the available to promise for week 6?